Changing a Working Day to a Nonworking Day While on the Change Working Time dialog box, you can make several different kinds of changes to the selected base calendar. Working times are displayed for the selected calendar day. For example, if the task must happen over a weekend but your project calendar specifies weekends as nonworking time, you can use a task calendar to call out that weekend as working time for just that task while leaving the rest of the project using the normal project calendar.įIGURE 3.7. Use task calendars to enter special days specific to individual tasks in your project.